New Rossano-Sibari line

Calabria, southern Italy, 2022-2024

Client ANAS Spa

In the framework of the modernization of the S.S. 106 Jonica, the new infrastructural link has been developed on new aligment to reach better levels of resilience of the existing north-south network, providing a viable alternative to the parallel A2 motorway on the Tyrrhenian front. The project involves the construction of a new road of “B” class according to the 2001 Decree, in the section between the Viaduct Coserie in the territory of Corigliano-Rossano and the SS534 Firmo-Sibari in the territory of Cassano allo Jonio. The project is completed by the upgrading on site of the SS534 for an extension of about 6 km between Megalotto 3 (road junction not included) and the intersection with the existing SS106 Radd. The route consists of a total length of about 32km, 5 km developed on viaducts.

E.D.IN., within the scope of the Technical and Economic Feasibility Design for D&B tendering, has been responsible for the structural and geotechnical design of about 20 dual and single carriageway viaducts along the new link. The structures comprise composite steel-concrete decks, bow-tie steel arch bridges and extradosed steel trusses.

Infrastrutture Stradali Nuovo collegamento Rossano-Sibari 1
Infrastrutture Stradali Nuovo collegamento Rossano-Sibari 2
Infrastrutture Stradali Nuovo collegamento Rossano-Sibari 3
Infrastrutture Stradali Nuovo collegamento Rossano-Sibari 4

New Catanzaro-Crotone line

Calabria, southern Italy, 2022-2024

Client ANAS Spa

In the framework of the modernization of the S.S. 106 Jonica, the new infrastructural link has been developed on a new aligment, to reach better levels of resilience of the existing north-south network, providing a viable alternative for the parallel A2 motorway on the Tyrrhenian front. In the development of the new route between the cities of Catanzaro and Crotone, the new link extends for about 50km, along which one finds about 20km of different structures, including tunnels and viaducts, for a total investment cost of about 2 billion euros.

E.D.IN., within the scope of the Technical and Economic Feasibility Design for D&B tendering, has been responsible for the structural and geotechnical design of about  40 separate dual carriageway viaducts along the new link. The structures consist of composite steel-concrete decks, with seismic protection provided by latest generation isolation systems.

Infrastrutture Stradali Nuovo collegamento Catanzaro-Crotone 1
Infrastrutture Stradali - Nuovo collegamento Catanzaro-Crotone 2
Infrastrutture Stradali - Nuovo collegamento Catanzaro-Crotone 3

Ramp 1B, Umm Lafina Project

UAE, 2022

Client WeBuild Inc.

The Ramp 1B flyover is part of a large infrastructural project ancillary to the Abu Dhabi – Dubai motorway link. The structure features a segmental box prestressed concrete deck with five continuous spans, maximum span length 114 m. The scope of work followed a number of issued occurred during the last construction stages and comprised the consultancy for the evaluation of the phenomena and for the rehabilitation design, numerical analyses of the erection stages with simulation of the damage and of the subsequent measures.

EDIN Infrastrutture Stradali - Umm Lafina 2
EDIN Infrastrutture Stradali - Umm Lafina 3
EDIN Infrastrutture Stradali - Umm Lafina 1
EDIN Infrastrutture Stradali - Umm Lafina 4

Storstrøm Crossing

Denmark, in progress

Clients Ramboll A/S, SBJV

The Storstrøm is a road, railway and pedestrian bridge that crosses the Storstrømmen between the islands of Falster and Masnedø. Of about 4 km total length offshore, with 80 m typical spans and as main crossing a single mast cable stayed bridge with two twin 180 m spans. E.D.In. is collaborating to the preparation of the construction drawings, with scope of work the substructures of the entire bridge.

Storstrøm
8 REV02
6 REV02
Storstrøm
Storstrøm
Storstrøm
Storstrøm
Storstrøm
Storstrøm
  • Storstrøm
  • 8 REV02
  • 6 REV02
  • Storstrøm
  • Storstrøm
  • Storstrøm
  • Storstrøm
  • Storstrøm
  • Storstrøm
  • Storstrøm

  • 8 REV02

  • 6 REV02

  • Storstrøm

  • Storstrøm

  • Storstrøm

  • Storstrøm

  • Storstrøm

  • Storstrøm

  • Storstrøm
  • 8 REV02
  • 6 REV02
  • Storstrøm
  • Storstrøm
  • Storstrøm
  • Storstrøm
  • Storstrøm
  • Storstrøm

Storebælt Crossing

Denmark, 1986-1987, 1988, 1994-1995

Clients Storebælt A/S, CMF Sud Inc, Coinfra Inc

The Storebælt Suspension Bridge is the main crossing in the Great Belt Fixed Link between the Danish islands of Zealand and Funen and, with its centre span of 1624 m, was when opened in 1998 the second worldwide. In a first phase E.D.In. participated to the International Board for the review of the design on behalf of the concessionaire Storebælt A/S, now Sund&Belt A/S. Subsequently acted as designer for CMF Sud for the participation to tender, winner, preparing the design for tender of global and minor alternatives, the latter accepted and introduced in the project, as well as designing a major alternative, accepted, for the access viaducts proposing a typical span of 193 m. Last, during the construction acted as expert witness for claims related to the steel deck erection on behalf of COINFRA.

Ref: F. Brancaleoni, R. Bartelletti, S. Caramelli, G. Diana, L. Sanpaolesi, THE EAST BRIDGE FOR THE GREAT BELT PERMANENT LINK: ITALIAN ROLE IN THE DESIGN, Atti Congresso Nazionale ‘Giornate Italiane della Costruzione in Acciaio’, Collegio Italiano dei Tecnici dell’Acciaio, CTA, Viareggio, October 1993.

1a REV02
Storaebelt 1b
Storaebelt 2
Storaebelt 3
Storaebelt 4
Storaebelt 5
Storaebelt 6
7 REV02

Miscellaneous Road bridges,
an overview

Detail and/or construction design of seven viaducts and five flyovers viaducts with composite deck, Southern Italy, Main Roads SS212 Fortorina, SS7 ter Bradanica, SS89 Garganica, SS658, 2017-in progress, Client Anas Inc

Construction design for repair and seismic upgrading of a flyover on the SS4 “Salaria” Main Road and of a masonry arch bridge, both struck by the 2016 earthquake, Central Italy, Client ANAS SpA, 2017

Himera viaduct, Palermo-Catania, construction design of piers and foundations for the new viaduct that replaced the carriageway torn down by a landslide, strengthening of existing piers and foundations, Client ANAS Inc, 2016

Construction design of a composite deck flyover, span 48m, on the new Rome-Neaples High Speed line, Central Italy, segment Cancello-Frasso Telesino, Client Italferr Inc, 2015

Proof engineering of the new Madonna del Monte viaduct, A6 Motorway, northern Italy, to replace the existing viaduct torn down by a landslide, proof engineer Giuseppe Grimaldi, Client Autostrada dei Fiori Inc, 2020

Construction design for a composite deck bridge on the Gurara River, Nigeria, Client Salini Impregilo, 2014

Shop drawings for the Petrace viaduct orthotropic steel deck, Salerno Reggio Calabria Motorway, southern Italy, Client Costruzioni Metalliche Prefabbricate Ltdl, 2007

Bridge on the Tiber for the Rome Ringroad at Castel Giubileo, construction design of piers and foundations, Client Tiber Consortium, 2005

Grana Viaduct for the SS1 “Aurelia” Main Road, Savona-Albisola segment, northern Italy, prestressed concrete voided slab continuous deck, detail design, Client ANAS Inc, 2003

SS106 “Ionica” Main Road, lot 2, southern Italy, arch bridges on the Fiumarella river and Corace viaduct, detail design, Client 3Ti, 2004

Detail and construction design of the Petroso viaduct, Salerno-Reggio Calabria Motorway, orthotropic steel deck, Client ANAS Inc, 2004

Bridge on the Tanagro river,Salerno-Reggio Calabria motorway upgrading, detail design, Client STE ltd, 2000

EDIN Infrastrutture Stradali
EDIN Infrastrutture Stradali
EDIN Infrastrutture Stradali
EDIN Infrastrutture Stradali
EDIN Infrastrutture Stradali
EDIN Infrastrutture Stradali

Road bridges, performances for traffic loads

E.D.In. is among the first engineering companies to have carried out the evaluation of allowable traffic loads for road bridges according to the Guidelines issued in 2020 by the Italian Ministry of Infrastructures

Cento viaduct, A6 Motorway, northern Italy, with eight spans for a maximum of 32m and prestressed concrete decks, Client Autostrada dei Fiori Inc, 2020

Impero viaduct, A10 Motorway, northern Italy, with eight prestressed concrete spans, maximum 70 m, and one ordinary concrete span, Client Autostrada dei Fiori Inc, 2020

Chiappa viaduct, A10 Motorway, northern Italy, comprising seven prestressed concrete 25m spans, Client Autostrada dei Fiori Inc, 2020

Roja viaduct, A10 Motorway, northern Italy, comprising sixteen prestressed concrete 22m spans, Client Autostrada dei Fiori Inc, 2020

Structural health assessment of the Ponte Giovanni XXIII on the Paola Lake, Sabaudia, Italy, design by Riccardo Morandi, comprising five 48 to 50 m spans, Gerber structural scheme, Client Sabaudia Municipality, 2016

EDIN Infrastrutture Stradali
EDIN Infrastrutture Stradali

Seismic vulnerability and SHM of road bridges

Numerous seismic vulnerability analyses of road bridges, all in Italy,carried out either within assessment activities or within their rehabilitation design. Among them:

Twelve prestressed concrete viaducts within the detail design of the doubling of the SS372 “Telesina” Main Road, Client ANAS Inc, 2019

ASTM Group concessions viaducts, comprising viaducts on SS335, Prerichard, Perilleux (A32), Marmore and Fenis (A5), Clients the Concessionaries, 2020

Flyover on the Salaria Main Road and masonry arch bridge damaged by the 2016 earthquake, within the construction design, Client ANAS Inc, 2017

Historical reinforced concrete viaduct, Nemi, Rome, Client CMRC, 2018

Himera viaduct, Sicily, within the construction design of the foundations and piers for the strengthening and replacement of the carriageway torn down by a landslide, Client ANAS Inc, 2016

Guidelines for the structural and environmental monitoring system, preliminary design, Messina Strait Bridge, Client Stretto di Messina Inc, 2002

Semi-permenent monitoring system, design, installation and operation, second Bosphorus Bridge, Istanbul. Client Stretto di Messina Inc, 1990-1992

Dynamic testing of bridge structures, A3 Motorway Salerno – Reggio Calabria, Client Tecnoproject Ltd, 1988-1989

Dynamic testing of the Gabbiano viaduct, A14 motorway,and of the Stura V viaduct, A26 motorway, Client Autostrade Inc, 2000-2002

EDIN Infrastrutture Stradali
EDIN Infrastrutture Stradali
EDIN Infrastrutture Stradali

Lift bridges

E.D.In. has designed a few lift bridges, comprising:

Detail design of a 30 m span bascule on the Fossa Traianea, Fiumicino, Rome, Italy, winner of an international design contest, Client Municipality of Fiumicino, 2006

Detail design of a 60 m span bascule bridge on the Candiano Canal, Ravenna, Italy, Client the Ravenna Harbour Authority, 2004.

Concept design of a 150 m span lift bridge on the Santos Harbour mouth, Brazil, Client Consorcio Serra Do Mar, 2011.

EDIN Infrastrutture Stradali Ponti Levatoi 1 Fiumicino
EDIN Infrastrutture Stradali Ponti Levatoi 2 Ravenna

Pantano Viaduct

Messina, Italy, 2010

Client SINA Inc

Detail design of the Messina Strait Bridge road and rail access viaduct on the Sicily side, Southern Italy. Conceived so as to recall the Man Crossing deck shapes, comprises simply supported composite rail spans and continuous orthotropic plate steel spans for the road carriageways, both with typical span of 73 m and a total length of 438 m.

EDIN_Infrastrutture_Stradali_Pantano_Messina
EDIN_Infrastrutture_Stradali_Pantano_Messina
EDIN_Infrastrutture_Stradali_Pantano_Messina
  • 1
  • 2
EDIN S.r.l.

E.D.IN. Ltd.
Consulting Engineers

Via Casilina, 3/t
00182 - ROMA
Phone.: +39 06 5452591
Fax.: +39 06 54525939
Email: info@ediningegneria.com
Vat Number: 01275921003
Codice Fiscale: 04016070585


Copyright Edin Ltd